How to quote a re-roof
The full method for a long-run steel re-roof in New Zealand — by hand or in software. Written from the way it is actually done, including the parts that go wrong.
Quoting a re-roof is six steps: measure the roof at its true pitch, count the sheets by run length, count the flashings piece by piece, add the consumables that follow from those two counts, price labour and access, then write a scope that says what is excluded. The step that costs people money is the third one — flashings counted as a total rather than as pieces, and sloped lengths not corrected for pitch.
1. Measure the roof — at the pitch, not on the flat
Everything starts with the plan shape: the outline of the building, and the internal lines that make it a roof — ridges, hips, valleys, barges, aprons. You can take that off an aerial photo, off the plans, or off a tape on site.
Then correct for pitch. A roof drawn in plan is flat, and the real roof is longer wherever
it slopes. The multiplier is 1 / cos(pitch):
| Pitch | Multiplier | A 4.00 m plan length is really |
|---|---|---|
| 10° | 1.015 | 4.06 m |
| 15° | 1.035 | 4.14 m |
| 20° | 1.064 | 4.26 m |
| 25° | 1.103 | 4.41 m |
| 30° | 1.155 | 4.62 m |
| 35° | 1.221 | 4.88 m |
| 40° | 1.305 | 5.22 m |
It applies to anything that slopes: sheet runs, rafter lengths, hip and valley lengths, barge lengths, and the roof area. It does not apply to the ridge or the gutter line, which are level. Applying it to everything is as wrong as applying it to nothing.
Hips and valleys need care: they run diagonally, so their true length is longer again than a simple rafter at the same pitch. If you are doing it by hand, measure them in plan and apply the pitch factor for the diagonal, not the rafter.
2. Count the sheets by run length
Long-run steel is cut to length, so what you are ordering is a set of lengths and quantities, not an area. For each roof face:
- Find the run length — ridge to gutter, at the pitch, plus the overhang into the gutter
- Divide the face width by the profile's cover width and round up
- Repeat per face, then group identical lengths together for the order
Cover width is the number that matters, not sheet width. Corrugate covers less than it measures because of the side lap — a nominal 860 mm sheet covers about 762 mm — and a trapezoidal 5-rib covers differently again. Using sheet width instead of cover width leaves you short on every roof: on corrugate you order 88.6 per cent of what you need — short by about one sheet in every nine.
One trap worth naming: a sheet run must be measured to the gutter that actually catches it. On a roof with a wing or a step-down, the nearest gutter in a straight line is often not the one the water reaches, and a run measured to the wrong one comes out metres long. It is a mistake that survives right through to the delivery.
3. Count the flashings — as pieces, not metres
This is where re-roof quotes go wrong, and it goes wrong in the direction that costs you.
Every roof line is a flashing: ridge along the top, hip down each external corner, valley up each internal one, barge along each gable edge, apron where the roof meets a wall, and change-of-pitch wherever the slope breaks.
Write them down as pieces at lengths — 1 @ 6.8 m, 1 @ 3.7 m — not
as a total. Forty-two metres of barge could be six pieces or fifteen, and the merchant folds
and cuts to length. A total is not an order.
Then the ones that get forgotten:
- Back-trays. Every pipe penetration needs a dektite and a back-tray behind it. The tray is the item that gets left off the docket and found on the roof.
- Boxed penetrations. A boxed chimney is five pieces, not one: a back flashing, two sides, a front apron, and a saddle running from the ridge down to the top of the box.
- Shared edges. Where two roofs meet, that edge is one flashing. Counting it on both roofs is the standard way a take-off comes out over.
4. Consumables follow from the counts
Once the sheets and flashings are counted, everything else is arithmetic off those two numbers:
- Underlay — by roof area, with the lap allowed
- Screws — by sheet metres and purlin spacing; count the ridge and eave rows separately, they are denser
- Rivets — by flashing metres
- Sealant — by the number of laps and penetrations
- Gutter and downpipes — gutter by the gutter line, downpipes by catchment; a downpipe serves a limited length of gutter and the count is a site decision
5. Price labour, access and disposal
Material is the easy half. Labour on a re-roof is driven by:
- Area and pitch. Above about 35° the work slows down noticeably and the access requirements change.
- Cut-up-ness. Hips, valleys and penetrations cost hours that area alone does not predict. A 200 m² hip-and-valley roof with four penetrations is a different job from a 200 m² straight gable.
- Storeys and access. Whether the truck can get to the eave.
- The strip. Removing the old roof, and carting it. Tile-to-steel means over-purlining as well.
Scaffolding or edge protection is its own line, and worth showing separately — it is a real cost the homeowner did not expect, and burying it in the rate makes the whole quote look expensive rather than the access looking expensive.
On disposal: the scrap value of the old steel roughly offsets the labour and time to strip and cart it. Whether the customer keeps it or you take it away tends to be a wash, so it is a genuine choice to offer rather than a charge to argue about.
6. Write the scope, and write the exclusions
A quote that lists a price and a product invites every argument later. Say what you are doing:
- Strip and dispose of the existing roof
- New underlay
- New long-run steel — by profile, grade, gauge and colour
- All new flashings, listed by type
- Guttering and downpipes, or explicitly not
- All penetrations reflashed
- Scaffolding or edge protection
- Site clean and make-good
Then what you are not doing, because this is the half that protects you: rotten purlins or framing found once the roof is off, asbestos or lead discovered in the strip, anything needing a building consent, painting, and internal damage from pre-existing leaks. Price the variation honestly when it appears; exclude it clearly before it does.
Choosing the material
Two decisions carry most of the cost difference, and both depend on where the house is.
Grade is about corrosion. Distance to breaking surf sets the zone, and the zone sets the warranty: mild is roughly 5 km or more inland, moderate 500 m to 1 km, severe 100 to 500 m, and very severe 25 to 100 m. Colorsteel MAXAM holds up best close to the sea; ColorCote is comparable; ColorZen is a cheaper pre-painted option that gives away corrosion protection in coastal zones; plain Zincalume is unpainted and self-weathering, the cheapest and the longest-lived where appearance does not matter.
Gauge is 0.40 or 0.55. On a normal residential roof 0.40 is standard. 0.55 buys stiffness underfoot, better performance across wider purlin spacings, and it is worth having in a severe coastal zone or on a roof people will walk on regularly.
What comes up most.
How long should quoting a re-roof take?
By hand, most of a day for a cut-up roof: measuring, working sloped lengths back through the pitch, counting flashings by type and piece, then writing it up. Measured off an aerial with the arithmetic automated, the same roof is twenty minutes to a proposal.
The part that takes the longest is not the maths. It is counting the flashings without missing any.
How much wastage should I allow on long-run steel?
On sheets, very little — long-run is cut to length, so the waste is the off-cut at the end of a run and the sheets ruined in handling. Two to five per cent covers most roofs.
Flashings are different: allow per piece, not as a percentage. Roughly 0.3 to 0.5 m per run for laps and end trims, rounded up to the next 0.1 m. A percentage on a total runs generous on a simple roof and short on a cut-up one, which is the wrong way round.
What is the biggest thing people get wrong?
Two things, and both are flashings.
First, forgetting the pitch factor on anything that slopes. At 25 degrees a sloped length is about 10 per cent longer than it looks on a plan; at 35 degrees, about 22 per cent.
Second, counting flashing metres as a total instead of as pieces. Forty-two metres of barge could be six pieces or fifteen, and the merchant folds to length.
Should I price a repair or a re-roof?
It depends on what is failing. Corroded fixings, a coating that has chalked through, or perforation at the laps means the roof is at the end of its life and a repair buys a season. A single storm-damaged sheet on an otherwise sound roof is a repair.
Put the assessment in writing either way. A homeowner who understands why it needs doing argues about the price far less.
Do I need to allow for asbestos or lead?
On anything pre-1990, check before you price it. Asbestos-cement roofing and lead flashings both change the strip cost and the disposal, and neither is something to discover on the day. Exclude it explicitly in the scope if you have not tested.
What should be in the scope of work?
What you are removing, what you are installing, what you are leaving, and what you are not touching. Specifically: the strip and disposal, underlay, the new roof by profile, grade, gauge and colour, all flashings, guttering and downpipes, penetrations and their flashings, scaffolding or edge protection, and the make-good.
Then the exclusions: rotten purlins or framing found once the roof is off, asbestos, anything requiring a consent, and painting.